By Adams Heating & Cooling Team Published
Quick answer
Replacing a furnace, boiler, air conditioner, heat pump or water heater typically needs a mechanical permit from your local building department. Around Kalamazoo the issuing office depends on where the home sits: some cities and townships run their own building department, some share one through the Kalamazoo Area Building Authority (KABA), such as Comstock and Richland, and some contract the work out. Call your local office to confirm before the job starts.
Published · Reviewed
Part of our Furnace Installation & Replacement guides.
This guide is general information, not legal advice. Permit rules change — confirm current requirements with your local building department before work begins.
What is an HVAC permit, and what does it cover?
An HVAC permit is written approval from your local building department to install or replace heating, cooling or ventilation equipment, and it registers the job so the work can be inspected against the code. In Michigan, mechanical work falls under the 2021 Michigan Mechanical Code, which has been in force since March 12, 2024. The City of Kalamazoo's mechanical permit, for example, covers installing equipment such as boilers, water heaters, air conditioning and gas fireplaces, along with other heating, cooling and ventilation work.
The permit is about the installation, not the brand or the price. It covers how the equipment is connected, vented and supported in your home: gas piping, flue and venting, combustion air, condensate and refrigerant lines.
The 2021 Michigan Mechanical Code has governed mechanical permits in Michigan since March 12, 2024.
Do you need a permit to replace a furnace, AC or water heater in Michigan?
Usually, yes. Replacing a furnace, boiler, air conditioner, heat pump or water heater typically needs a mechanical permit from your local building department. The City of Portage, for example, requires one to replace a mechanical system, and the City of Kalamazoo lists water heaters, boilers and air conditioning as mechanical-permit work.
Typical jobs that call for a permit:
- Replacing a gas furnace or boiler
- Adding or replacing central air conditioning or a heat pump
- Installing a ductless mini-split
- Replacing a gas or electric water heater
- Switching from an 80% furnace to a 90%+ furnace, which changes the venting
Water heaters raise their own permit and licensing questions; our guide Do You Need a Permit to Replace a Water Heater in Michigan? covers that in detail.
Replacing a furnace, air conditioner, heat pump or water heater typically needs a mechanical permit from your local building department.
Who issues HVAC permits in Kalamazoo County?
HVAC permits around Kalamazoo are issued locally, and the issuing office depends on where the home sits. Some communities run their own building department, some share one through the Kalamazoo Area Building Authority (KABA), and some contract the work to a private code agency.
| Community | Type (county) | Mechanical permits issued by |
|---|---|---|
| Kalamazoo | City (Kalamazoo) | City of Kalamazoo, Community Planning & Economic Development |
| Portage | City (Kalamazoo) | City of Portage Building Division (licensed mechanical contractor or owner-occupant) |
| Oshtemo | Charter township (Kalamazoo) | Oshtemo Charter Township Building Department |
| Comstock | Charter township (Kalamazoo) | Kalamazoo Area Building Authority (KABA) |
| Richland | Village and township (Kalamazoo) | Kalamazoo Area Building Authority (KABA) |
| Mattawan | Village, Antwerp Township (Van Buren) | Village of Mattawan (inspector through Antwerp Township) |
| Lawton | Village (Van Buren) | SAFEbuilt |
| Plainwell | City (Allegan) | Professional Code Inspections (PCI) |
Other communities: check with your city or township office, or Michigan's Bureau of Construction Codes (LARA).
HVAC permits around Kalamazoo come from the local city, village or township office, or from the building authority or code firm it works with.
Can a homeowner get the permit, or does it have to be a contractor?
It depends on the community and on who lives in the home. The City of Portage issues mechanical permits to a licensed mechanical contractor or to an owner-occupant. The City of Kalamazoo lets a homeowner apply if they are the owner the building department has on record, and it requires work on rental properties to be completed by a licensed contractor.
Before work starts, ask whoever is doing the job who will apply for the permit, and ask to see the permit number. If your community is not in the table above, your city or township office can tell you whether owner permits are allowed there.
The City of Kalamazoo requires work on rental properties to be completed by a licensed contractor.
What goes wrong when HVAC work skips the permit?
Unpermitted HVAC work has no inspection record, which means no one independent has checked the gas connection, venting or combustion air against the code. Those are the parts of a heating installation that matter most for safety, and they are hard for a homeowner to judge by looking.
A few common trouble spots:
- Venting changes. Moving from an 80% furnace to a 90%+ furnace changes how the furnace vents, and that new venting is part of what the permit covers. Our blog post on furnace vent clearances under Portage codes walks through why clearances matter.
- Wrong office. Applying to the township when the village enforces the code (or the reverse) delays the job. Richland's village and township, for example, both go through KABA, while Mattawan's village uses an inspector through Antwerp Township.
- Old rules. Code editions and federal equipment rules change. New refrigerants and efficiency minimums affect what can be installed; see R-454B and R-32: What the New A2L Refrigerants Mean for Your Next AC or Heat Pump.
A permit is the only independent record that a heating installation's gas, venting and combustion air were checked against the code.
How can you check a permit before your new system goes in?
You can confirm a permit by calling the issuing office in the table above with your address. Every source on this page is a public city, township or building-authority document, listed under Sources below, so you can read the rules yourself.
A short checklist for a replacement:
- Find your issuing office in the table, or call your city or township office.
- Ask whether the job needs a mechanical permit, a plumbing permit or both.
- Ask who will apply for the permit and when the inspection will be scheduled.
- Keep the permit number and inspection result with your equipment paperwork.
Adams Heating & Cooling has been a family-owned Kalamazoo company for 30+ years, and replacements and new installations start with a free estimate. Bring your permit questions to that visit.
Keeping the permit number with your furnace or AC paperwork gives you a record of the inspection for the life of the system.
Frequently asked questions
Do I need a permit to replace my furnace in Kalamazoo?
Yes. The City of Kalamazoo lists heating work as mechanical-permit work, and that permit is issued by Community Planning & Economic Development.
Who issues HVAC permits outside the City of Kalamazoo?
Permits come from your local city, village or township, or from the Kalamazoo Area Building Authority (KABA) for member communities such as Comstock and Richland. Call your local office to confirm who issues permits at your address.
Who issues mechanical permits in Portage?
The City of Portage Building Division issues mechanical permits, to a licensed mechanical contractor or to an owner-occupant.
Can I pull my own HVAC permit as a homeowner?
In some communities, yes. Portage allows owner-occupants, and the City of Kalamazoo allows the owner on record, but Kalamazoo requires rental-property work to be done by a licensed contractor. Check with your local office before you apply.
Which code applies to HVAC work in Michigan?
Oshtemo Charter Township, for example, lists the 2021 Michigan Mechanical Code, effective March 12, 2024, as its current mechanical code.
My community is not in the table. Where do I ask?
Call your city, village or township office; it can tell you who enforces the mechanical code at your address.
Sources
- City of Kalamazoo — Apply for a Mechanical Permit (accessed November 19, 2026)
- City of Portage — Mechanical Information Sheet (accessed November 19, 2026)
- Oshtemo Charter Township — Mechanical Permit Application (accessed November 19, 2026)
- Kalamazoo Area Building Authority — Home (accessed November 19, 2026)
- Richland Township — Building Department (accessed November 19, 2026)
- Antwerp Township — Mattawan Permits (accessed November 19, 2026)
- Village of Lawton — Planning & Zoning (accessed November 19, 2026)
- City of Plainwell — Building Department (accessed November 19, 2026)
- Oshtemo Charter Township — Codes Currently in Effect (accessed November 19, 2026)